Plans to install a two-way protected cycle lane have been delayed after a business owner objected to the proposal, arguing it would have a “devastating impact” on the business by restricting “essential operational access” for the business. That’s despite the council confirming the plans would not change the current waiting and loading restrictions for vehicles outside the shop.

Sunderland Models sits on Ryhope Road, where the council is planning on constructing a 3.8km (2.4 miles) two-way protected cycle lane running from the edge of Mowbray Park in the city centre, south through Grangetown towards Ryhope beach and cliffs.

The business sits near a roundabout in Grangetown, and at present has no direct vehicular access from the front of the premises.

However, the business already has private rear access to the premises and the council say that “the waiting and loading restrictions proposed outside the premises are unchanged from those currently in place. The scheme does not, therefore, introduce additional restrictions at this frontage.”

Despite this, the business’ objection remains in place, with the owner, whose name is omitted from published documents, writing, “my objection is raised on the grounds of severe economic detriment and the restriction of essential operational access for my business.

“During the initial planning consultation phase, I formally requested that a dedicated loading bay be integrated into the plans outside or adjacent to my premises to accommodate essential commercial deliveries and servicing. Upon reviewing the published maps, I note that this loading bay has been entirely omitted.

> Plans to remove “white elephant” cycle lane and reopen road to motorists in both directions rated “net positive” for environment by the council

“Instead, the proposed layout implements sweeping new waiting and loading prohibitions that completely cut off my business from safe, legal servicing except via the crowded and unfit for purpose rear access lane.

“Operating without a designated loading area will have a devastating impact on our day-to-day operations. It will prevent suppliers from safely offloading goods, effectively threatening the long term viability of the business.

“While I understand the council’s ambition to improve sustainable transport via the Ryhope Road Cycle Scheme, it must not come at the absolute expense of pre-existing local businesses. The total omission of the previously requested loading bay fails to strike a fair and proportionate balance between cyclists and the local economy.

“I urge the council to defer the implementation of these specific restrictions along this section of Ryhope Road until the scheme design is amended to incorporate the vital loading provision requested during the initial consultation.”

Responding to the objection, council officers recommend the business owner contacts local landlords and nearby businesses to arrange more formal parking and delivery arrangements at the back of their building.

> Work on controversial Bath cycle lane delayed after council admits it forgot to respond to formal objection

“Officers considered the request for a dedicated loading bay during the design process and following the engagement stage. However, provision could not be accommodated within the highway constraints at this location, including the requirement to retain the bus stop outside the premises.”

“Having considered the objection, the assessment set out in this report and the council’s duties, […] officers consider that the proposals strike an appropriate balance between the needs of highway users and the access and servicing concerns raised. On
that basis, officers consider it necessary to support the safe and effective operation of the revised highway layout.”

However, due to the business owner maintaining his objection, the council are unable to go ahead with construction of the cycle lanes, and are instead set to defer a formal decision whilst seeking legal clarification on whether a public inquiry should be held due to the claimed impact on vehicle loading or unloading.

Work was initially due to begin on the cycle lane last summer and be finished by spring 2026, however the objection has delayed the proposal. Proposals for the cycle lane include Dutch-style roundabouts, maintained physical separation between motorists, cyclists and pedestrians, improved signalling at junctions and the installation of “secure cycle storage” along the route.

Sunderland Ryhope Road proposal roundabout
Sunderland Ryhope Road proposal roundabout (Image Credit: Sunderland City Council)

The project is not directly funded by the council and instead backed by the Department for Transport’s Active Travel Fund and the North East’s City Region Sustainable Transport Settlement scheme.

That funding arrangement partly insulates the cycle lane from local political influences, with the council able to use the allocated funding “for the purposes of cycling infrastructure only”. In the local elections in May earlier this year, the Labour Party lost control of the council after 52 years to Reform UK. Reform now holds 57 of the council’s 75 seats.

However, despite the council’s change in governance and past statements from the party’s leadership, Reform councillors have recently welcomed the introduction of a Brompton bike hire scheme in the city.

> Reform council welcomes Brompton hire scheme

Councillor Bill Blackett, the council’s Cabinet Member for Environment and Transport Enforcement, said: “Whether you’re commuting, travelling onwards from the railway station, exploring the coastline or visiting other fantastic attractions, this Brompton Bike Hire offers a flexible, affordable and sustainable way to get around.”

The council has also heralded the “more than 60 miles of dedicated cycling routes, including over 50 miles of traffic-free paths, linking the city centre with neighbourhoods, coastline and countryside” as well as several significant major cycle routes nearby such as the Coast to Coast Cycle Route and National Cycle Network Routes 1 and 70.