Support road.cc

Like this site? Help us to make it better.

news

Work begins to resurface Herne Hill Velodrome track

Money provided by new tenant British Cycling and bequest from local club member Leonard Lyes

British Cycling has confirmed that work is now under way to resurface the track at the historic Herne Hill Velodrome, the last surviving venue from the London 1948 Olympic Games, the first major work at the facility since a 15-year lease was signed between the sport’s governing body and the site’s landlords, The Dulwich Estate.

The poor condition of the track has been blamed for some events, including the Good Friday Meeting, being relocated to other venues, although in the case of the latter, the weather has also been influential, with this year’s event taking place indoors at the Manchester Velodrome following a washout in South London 12 months earlier.

The future of the track had been thrown into doubt after The Dulwich Estate revealed that it planned to redevelop the site, where generations of British cyclists including three-time Olympic gold medallist Bradley Wiggins got their start on the track.

That resulted in the Save The Velodrome campaign being mobilised to try and preserve the site for track cycling, drawing on the support of public figures not only within the sport but also those from the worlds of politics and entertainment living nearby.

The work has been financed by money provided by British Cycling under its Whole Sport Plan, together with a bequest from the estate of Leonard Lyes, who died in July 2009 and was a member of the De Laune Cycling Club, regularly officiating at Herne Hill.

Mr Lyes had requested that his bequest be used “in the pursuit of track cycling,” and Ian Drake, chief Executive of British Cycling, said he believed he would have approved of how the money was being spent.

“I don’t doubt that Leonard would be pleased that his generous donation is having such an impact at a venue that would close to his heart,” he commented.

“Getting the track repaired is a huge step forward for the Save the Velodrome campaign and will provide riders of all ages with a fantastic surface on which to enjoy their cycling. Herne Hill is such an iconic venue and British Cycling is both delighted and proud of the role it is playing in helping getting it back to its former glory.”

Hillary Peachey, Chair of the Save the Velodrome Campaign, said: "These works are a turning point for the Herne Hill Velodrome. Barely a year ago the future of this incredible site was uncertain; the lack of a long term lease combined with a series of harsh winters was threatening to overcome all the hard work which has been put in to the track over the decades and there was a very real threat of closure.

“At the launch of our campaign to save the Velodrome in late 2010, the Herne Hill Velodrome Trust's immediate aim was to secure a long term lease on the track in order to unlock the funding British Cycling had allocated to resurfacing. British Cycling's dedication to the project and professional approach resulted in the lease we needed and we all have an immense debt of gratitude to the team.

“And so as the physical works begin on the track, the Trust itself is now fundraising in earnest to bring together the plans and strategy needed to make the site a viable cycling venue for long in to the future. In time we will be drawing up proposals and inviting cyclists, local residents and politicians to tell us what they think, before we submit a planning application to Southwark Council. And of course, we are all looking forward to that first spin on the new track".

John Major, Chief Executive of The Dulwich Estate, added: “The Dulwich Estate is delighted that the track resurfacing is underway, ensuring that cycling can continue at this historic site.”

The work will take around six weeks to complete, with British Cycling’s Facilities Officer Patrick Flanagan outlining what is required to be done: "The track does need extensive structural repairs. It currently has a concrete base with an epoxy resin finish. This finish has failed and cracked, allowing water to enter the structure and, in conjunction with frost, cause extensive damage, alongside some settling of the concrete base."

"The repairs will start with this concrete base, which will be mended with fibre-glass reinforcement at each joint - it was originally made in 10 metre lengths and where these join, unevenness is now a problem. The repairs will provide a strong and very smooth base upon which the new track surface can be laid."

"The track will then be re-surfaced with a special velodrome-specific covering called ‘MasterTrack', a product we developed in conjunction with Tarmac. MasterTrack contains very fine granite stones and is exceptionally smooth, hard and dense, making it ideal for track racing. It is also impervious to water, so damage from the elements will be eliminated."

"The new surface will be 7 metres wide and laying it presents some challenges: its width, combined with the camber, which changes in the bends, and the need for an extremely smooth finish, make it remarkably difficult to lay. Tarmac has developed a unique rig which runs on a track inside the cycling track: this allows them to lay the surface in three wide strips. So, all in all, it's a pretty special project with some unique problems and equally unique solutions."

Updates on progress will be provided at www.britishcycling.org.uk and www.savethevelodrome.com.
 

Simon joined road.cc as news editor in 2009 and is now the site’s community editor, acting as a link between the team producing the content and our readers. A law and languages graduate, published translator and former retail analyst, he has reported on issues as diverse as cycling-related court cases, anti-doping investigations, the latest developments in the bike industry and the sport’s biggest races. Now back in London full-time after 15 years living in Oxford and Cambridge, he loves cycling along the Thames but misses having his former riding buddy, Elodie the miniature schnauzer, in the basket in front of him.

Add new comment

2 comments

Avatar
antonio | 12 years ago
0 likes

good news for track cycling heritage, good news for cycling.

Avatar
skippy | 12 years ago
0 likes

DElighted to see that that the work has finally started to prepare this track for use as one of the training venues for the 2012 London Paralympics & Olympic Games !

Why it has taken so long considering the track's historic importance is now irrevelant BUT it should serve as a reminder that there are other "Historic Venues " that also need saving and should not be left and neglected until the penultimate second !

To all those that contributed to the effort , WELL DONE !

Latest Comments